By Chris Morris on Thu, 5 Jan 2012
News: Dunedin | DCC
A public hearing next month will help decide what to do about erosion problems threatening Dunedin's Middle Beach.
The Dunedin City Council has been investigating the problems, and what to do about them, since severe storms in 2007 first highlighted the threat of erosion to Kettle Park and other facilities in the area.
That resulted in a draft Ocean Beach management plan prepared by consultant Tonkin and Taylor last year, covering a 4km area stretching from St Clair to Lawyers Head.
The draft plan recommended continuing the council's holding pattern of monitoring and sand-replenishment work - put in place after the 2007 storms - in the meantime.
However, the report also canvassed 13 longer-term options and recommended a managed retreat from Middle Beach and Kettle Park, or construction of an inland buried backstop wall to protect the area over the next 10 to 50 years, at an initial estimated cost of between $8 million and $19 million.
Yesterday, council community and recreation services manager Mick Reece said public consultation on the draft plan had prompted 17 submissions, including input from the Department of Conservation and individuals.
About half supported the draft plan's recommendations, while the rest had mixed views, he said.
A public hearing, set down for February 21 to 23, would be held to help determine a way forward, Mr Reece said.
chris.morris@odt.co.nz
A clay cap stretching 150m on top of sand dunes at Dunedin's Middle Beach has been removed by Dunedin City Council contractors, amid concerns further erosion could have caused it to collapse. Photo by Craig Baxter.
As waves continue to erode Dunedin's Middle Beach, major excavations have been carried out in recent weeks to remove a clay cap covering sand dunes, which was at risk of collapse.
you have until 5pm today to send in your submission for Ocean beach, i haven't even started writing mine!!
Closes: 25/11/2011 In 2008, the Council appointed a Project Team to gather data and consider management options for Ocean Beach. This followed significant erosion on the beach in June/July 2007, the DCC’s replenishment of sand on the beach and other remedial works as part of a now established ‘holding pattern’, and a comprehensive consultation process. Since then the Project Team has gathered and analysed that data and completed a risk assessment process. It has now identified proposed management options for Ocean Beach, taking into account the existing processes and risks. A report from Tonkin & Taylor dated October 2011 entitled: ‘Ocean Beach, Coastal Issues and Options’, sets out preferred options for managing the area using an adaptive management approach. The report is available for inspection at the DCC’s Customer Services Centre and Libraries from Tuesday 25 October during their ordinary opening hours. A summary of intent and submission forms are also available. The information, plus background material on erosion at Ocean Beach, can be found at www.dunedin.govt.nz/consultation. Submissions must be received by 5.00 pm on Friday 25 November. Hearing dates have been scheduled for Tuesday 31 January to Thursday 2 February 2012. Please state in your submission whether or not you wish to be heard. The public meeting is to be held on Monday 7 November 2011 at 7.00 pm. The venue is the Port Otago Room, first floor, Edgar Centre, corner Portsmouth Drive and Teviot Street. All interested members of the public are cordially invited to attend. A summary of the options and submission forms will also be available at the meetingProposed Management Options for Ocean Beach
Consultation documents
Consultation details
Closing date 25/11/2011 Contact person Business Development Team Leader Public feedback Public meetings
St Clair ramp damaged again
By David Loughrey on Sat, 1 Oct 2011
The Dunedin City Council confirmed yesterday fences and signs were being installed along the edge of the sports ground in the interests of public safety, and power had been disconnected from the sports field lights.
The work is expected to cost about $60,000.
"A further inspection of Ocean Beach was held this morning following our monitoring of the latest pattern of storm activity," council parks manager Lisa Wheeler said yesterday.
"It is now clear that the erosion of the dunes adjacent to Kettle Park on the eastern side of Moana Rua Rd requires remedial work."
Dunedin man John Piper, who walks his dog on the beach each day, raised concerns about the issue this week, after he noticed heavy seas had eroded sand dunes to within metres of light poles at the ground.
The council is coming to the end of an extended consultation and research period, as it tries to find a way to deal with the constant erosion at the beaches from St Clair to Lawyers Head, which was made worse by severe storms in 2007.
The council has been shoring up the dunes since then, dumping extra sand and placing "reno blankets" - rock-filled wire netting - along the beach.
Yesterday, community and recreation services manager Mick Reece said a rip had formed at Middle Beach.
The council has a stockpile of sand at Tahuna, which it dredged from Otago Harbour, and 5000cu m would be used to replenish the beach.
Contractors would also attempt during low tides to remove rubble from the beach that had been dumped there in the past, but had been exposed.
Ms Wheeler said the swell at the beach was predicted to ease yesterday, and work was being organised to begin next week to replenish the dunes most severely affected.
In 2009, the council set aside $400,000 for the following three years to deal with the problems until a longer-term solution was found.
There has been some erosion of the dune face at various points along the beach due to recent swell activity, mostly in the area located between The Esplanade, St Clair and the Moana Rua Road, St Kilda. Contractors have been instructed to remove overhanging sections of dune in areas where the face has been eroded to prevent clay capping material from falling onto the beach. Due to a lowering of sand levels, the stairway from the gravel track between the St Clair seawall and the tennis courts has been closed and the lower sections removed. This section of track may also be at risk of erosion during a predicted storm event and therefore will be closely monitored and repair works arranged where necessary. A report outlining the Project Team's preferred management options for the long term coastal protection of Ocean Beach and requesting approval to publicly consult on these options is being presented to the Community Development Committee on 7th September.